Substantial modernisation

Substantial modernisation takes place when the planned modifications to an installation deemed to be existing (production or consumption), on the basis of the assessment criteria defined by Elia, mean that this installation complies in full or in part with the requirements applicable to new installations.

A substantial modernisation can be defined as a modification of an existing installation (as defined in the European RfG and DCC codes and specified in the Royal Decree on the Federal Grid Code and in the decisions of the regulators:

  • VREG: Decision 2019-06
  • CWaPE: Decision CD-18j25-CWaPE-0233
  • Brugel: Decision 20190424-91)

that meets the criteria of the Guidelines defining the concept of "substantial modernisation" at the federal or regional level.

If a grid user (producer) intends to make modifications to a generation unit that is considered to be existing, such as an increase in capacity or a renewal of equipment, and these modifications meet the criteria set by Elia for substantial modernisation, then the existing generation unit must partially or fully comply with the requirements that apply to new generation units.

If a grid user (consumer) intends to make modifications to a consumer installation connected to the transmission system that is considered to be an existing installation, for example the renewal of equipment, and these modifications meet the criteria defined by Elia for substantial modernisation, the renewed element must fully comply with the requirements applicable to new consumer installations.

Legal framework

European Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (European Network Code RfG) and European Commission Regulation (EU) 2016/1388 of 17 August 2016 establishing a Network Code on Demand Connection (European Network Code DCC) define the requirements for the connection of new electricity generation facilities and consumer facilities. These requirements are included in the Royal Decree on the Federal Grid Code and in the decisions of the regulators VREG, CWaPE and BRUGEL on the general application requirements.

Article 4.1, a) of the European Network Codes RfG and DCC states that the requirements of these European Network Codes apply to generation and consumption installations that are considered as existing installations in the case of modernisation. At federal level, Article 4.1 of the European Grid Codes RfG and DCC are implemented in articles 71, §1, 1°, 161, 162 and 163 of the Royal Decree on Federal Technical Regulations.

In accordance with article 162(2) of the Royal Decree on Technical Regulations, Elia has drawn up guidelines on the definition and application of substantial modernisation. These have been the subject of a public consultation and extensive discussions with the market parties. These guidelines were then submitted for the advice of CREG and the DG Energy of the FPS Economy. At regional level,

  • In Flanders, article 4.1 of the European grid codes RfG and DCC has been implemented in the Technical Regulations Local Transport Network of Electricity in Articles III. 3.1.3 and III. 3.1.4 for consumer installations and in articles III.3.2.2 and III.3.2.3 for electricity production units.
  • In Wallonia and Brussels, Article 4.1 of the European Network Codes RfG and DCC applies to the local and regional transmission system respectively.

For this reason, Elia has also drawn up guidelines applicable at regional level, including the definition of a substantial modernisation, the criteria for a substantial modernisation of an electricity generation unit or a consumption unit and an application procedure. These guidelines were also the subject of a public consultation and were discussed in detail with market parties. These guidelines were then submitted to VREG for approval and to the CWaPE and BRUGEL just for information. Based on these guidelines, Elia will analyse whether the modifications made to an existing electricity generation or consumption facility constitute a substantial modernisation and will issue an opinion on the matter to the competent regulator. Ultimately, the regulator will decide whether the modernisation is substantial and, taking into account the criteria proposed by Elia, will set the requirements for new facilities that the existing facility being modernised must meet.


This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult our Cookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.