Gerpinnes-Hanzinelle

Installation of a 12.6 kV (medium voltage) underground connection between the Gerpinnes and Hanzinelle substations in order to secure the region’s supply.

banner
  • texte Benefits to society

    To secure the region’s supply

    In order to ensure the reliability of the electricity grid and the security of supply of the area, Elia, the transmission system operator in Belgium, will install an underground connection with a voltage level of 12.6 kV (medium voltage), over a length of 7.4 km in the municipality of Gerpinnes and the town of Florennes.

  • texte Interactive map

    Interactive map of the site:

  • Schedule
    According to the provisional schedule, this project will begin in October 2022 and end in March 2024. Above is an interactive map updated with the progress of the project and the potential impacts on mobility.
  • doc Documents

Contact us

If you are affected by a project and want to ask us something, please feel free to contact us.
Our team would be happy to help.

This website uses cookies to provide you with an optimal browsing experience. Some cookies are strictly necessary for the operation of this website and cannot be rejected, while others are used for analytical/functional/targeting purposes and can be rejected. For more information, please consult our Cookie Policy . You can manage/change your cookie preferences at any time. If you do not manage your preferences, only the cookies which are strictly necessary will be accepted.